Ivory stucco residence with charcoal bay windows, a recessed walnut entry door, concrete steps and a camellia beside the sidewalk.

The Gashouse Cove Plan Goes Before BCDC Today. Here's What Changes on the Marina Waterfront, and When

November 5, 2026

"This is going to be a beautiful waterfront recreational area, and I can't wait to get my paddleboard in the water there." Recreation and Park Commission chair Kat Anderson said that in April, after the commission voted unanimously to approve the concept design for the Marina Improvement and Remediation Project, as the San Francisco Chronicle reported.

She put the water first, and so does the plan. The project goes to the San Francisco Bay Conservation and Development Commission at 1 p.m. today, Thursday, November 5, as Agenda Item 8 at the Metro Center, 375 Beale Street. BCDC staff recommends 252,012 square feet of new public access in the Bay itself and 19,470 square feet in the shoreline band. That means more than 90 percent of the new public space at Gashouse Cove is water. Under the BCDC schedule, the East Harbor docks and fuel dock come out in 2027, but the replacement docks and the park are not complete until 2029.

What the East Harbor gives up

The project started with a cleanup. Gashouse Cove was the site of a 19th-century power plant, and PG&E is cleaning up the cove under a legal settlement with the city. That work means moving boat slips out of the East Harbor. An earlier version would have put about 185 slips in the West Harbor and blocked views from Marina Boulevard. The Board of Supervisors scrapped it in February 2024.

The current plan cuts the East Harbor by 170 slips, leaving 536 city-owned slips across the East and West harbors, and adds slips north of the East Harbor breakwater, away from the Boulevard sightlines. Anyone walking the harbor this year has already seen the start of it. The Chronicle reported in April that most boats in the southern section had moved to open slips farther north or left, and many of the crumbling wooden piers were gone. Those slips are not coming back.

The Gashouse Cove fuel dock goes too. It has been in the East Harbor for generations and is one of the few public fuel docks in San Francisco. Under the plan it moves to the West Harbor near St. Francis Yacht Club, and the design for that new dock has not been finalized.

What replaces it, measured mostly in water

The staff recommendation spells out public access for walking, cycling, sitting, viewing, picnicking, fishing and boating. These are the pieces a Marina neighbor would use:

  • A 5.7-acre shallow-water recreation basin in the nearshore area where the southern slips used to be, set aside for kayaks and other nonmotorized craft.
  • A community dock that staff says must be open to the public from 6 a.m. to 10 p.m.
  • A 1,560-square-foot breakwater walkway.
  • A rebuilt Bay Trail segment about 1,460 feet long and roughly 12.1 feet wide, along about 32,000 square feet of East Harbor shoreline.
  • Beach volleyball courts, a picnic area and a small plaza, plus nature exploration areas, new planting, lighting and furnishings.
  • 126 free public parking spaces kept around the East Harbor, along with a loading stall for the community dock. The parking lot drive gets narrower and gains accessible spaces.

The Chronicle describes the finished project as an expanded 5-acre public park next to Marina Green. The basin by itself is larger than that, which tells you where the plan puts its weight. The new amenities on land sit along a narrow edge. The new public room is out on the water, open to anyone with a paddleboard, a kayak, or a seat on the breakwater walkway. That is a different use of the harbor from the boat storage it has held for decades.

The project has supporters on land too. San Francisco Beach Volleyball, Inc. is listed in the April staff report as supporting the concept design. Rec and Park also reported meeting with St. Francis Yacht Club, Golden Gate Yacht Club, the Marina Harbor Association, South End Rowing Club, the Dolphin Club and the Sierra Club.

The order of work: demolition in year one, completion in year three

The schedule matters most for anyone who uses this stretch every day. The BCDC staff summary dated October 23, 2026 says construction could begin as early as fall 2027 and would run three years.

Year Work on the water Work on land
2027 East Harbor docks and fuel dock demolished; East Harbor dredged and capped; part of the East Harbor shoreline rebuilt; West Harbor breakwater built Upland park construction begins; crane demolished; underground storage tanks removed
2028 East Harbor and West Harbor docks built; East Harbor breakwater extended; dredging and capping outside the East Harbor Rest of the East Harbor shoreline rebuilt
2029 Dock construction completed Upland park construction completed

The East Harbor docks and fuel dock come out in the first year. The replacement docks, including the new West Harbor slips, are built in the second. Docks and park are both finished in the third year, although park construction starts in 2027. The estimated total cost is about $221.6 million.

Most of the first two years is PG&E's cleanup. Its plan calls for dredging the contaminated sediment, sending it to an approved reuse or disposal site, capping what remains, and installing a permeable reactive barrier along the shoreline to treat groundwater, with monitoring afterward, according to the Water Board fact sheet published by PG&E. The staff recommendation puts that at roughly 37,000 cubic yards dredged from about 7.4 acres, with a cap 1.5 to 2.5 feet thick over 7.89 acres. PG&E has to submit a final Remedial Action Plan before construction starts. The May 2026 fact sheet expected the plan to be finalized in late 2026, with cleanup over 2027 and 2028.

Why the fuel dock draws the sharpest objections

The fuel dock is where the order of work matters most. It is on the 2027 demolition list, and the West Harbor docks are scheduled for 2028. At the April hearing, the Chronicle reported, the dock's longtime operator told commissioners it has fueled fireboats during waterfront emergencies, and Anderson said fuel service would not be interrupted during construction.

The Harbor Safety Committee of the San Francisco Bay Region has since objected to removing the dock on maritime safety and access grounds. Its September 2026 letter says the committee's concerns came from discussions with emergency responders, marina operators, the San Francisco Bar Pilots and other maritime stakeholders. Boat owners who fuel at Gashouse Cove will want to follow this part of the plan most closely.

What walkers and runners can count on during construction

The staff recommendation does not set dates for closing any part of Marina Green, the waterfront path, the Gashouse Cove lot or the East Harbor. It sets rules instead. Construction has to keep impacts on existing public access to a minimum. If a section has to close, the conditions require a continuous marked detour, signs giving the length of the closure and the detour route, and BCDC review of the detour and signage plan before work starts. The area then has to be restored afterward.

The recommendation also sets deadlines. Construction must start before December 31, 2027 and finish by December 31, 2029. The required public access improvements are due within one year of project completion or by December 31, 2030, whichever comes first, and they must be ADA accessible. All of these are staff recommendations for today's hearing and possible vote. They become permit conditions only if the commission adopts them.

Following this afternoon's hearing

The BCDC November 5 meeting page has the agenda, the supporting materials and instructions for public participation, including the staff summary and the staff recommendation quoted above. Rec and Park's project page has the design. The city's October 30 notice lists project manager Monica Scott at [email protected], the harbor master at [email protected] for Marina Yacht Harbor questions, and [email protected] or (415) 973-0270 for questions about PG&E's cleanup.

Today's hearing, and a vote if the commission takes one, sets the conditions. The shoreline won't look much different until fall 2027 at the earliest, when the East Harbor docks and the fuel dock come out and the dredging begins.

A public basin and a community dock open from 6 a.m. to 10 p.m. will change what it means to live a few blocks from the East Harbor, and that will matter when homes along the waterfront are valued over the next few years. If you own near Marina Green and want to know how the 2027 to 2029 work could factor into your home's value, Mandy Lee will go through it with you. Request a free home valuation.

Work With Mandy

Innovative real estate maven hailing from the heart of San Francisco. Born and raised in this iconic city, I use my deep local roots with modern strategies, reshaping the real estate landscape. With an intimate knowledge of the city's diverse neighborhoods and a knack for design, she's your guide to finding the perfect property match.